We separately sum four values: the number of Benefits, the amount of Benefit Value, Number of Points and Emissions Savings supposed to have be delivered (i.e. the Final Delivery Date has passed and they have not been Substituted) in the Benefits within a Contract at any one time.

We separately compare these four values against the amounts of each delivered so far in Benefits that are marked as Delivered or Partially Delivered*, within this same Contract.

For each of the four values, if they are at 100%, when the Contract is In Progress or Completed, then they will show as Green.

For each of the four values, if they are between 80 and 100%, when the Contract is In Progress or Completed, then they will show as Amber.

For each of the four values, if they are between 0 and 80%, when the Contract is In Progress or Completed, then they will show as Red.

*In order for Partially Delivered Benefit values to be measured, Buyer Contract Managers have to enter Delivered Benefit Value, Delivered Number of Points and Delivered Emissions Savings on the Edit Benefit view, once they have selected Partially Delivered as the Benefit Status.